Pet Crematorium Build-Out and Equipment Installation
CPS set and rigged the equipment and ran new gas service, electrical, HVAC, and plumbing. We also handled permits and carried the work through final inspection.
The facility opened with its equipment running, giving the client a space ready to begin operations.
Reno, Nevada
Four-Unit Commercial Renovation
We coordinated electrical and interior work across four adjoining commercial units, 17 through 20, under one schedule and one point of contact.
The units were finished in sequence so the owner could take them back one at a time.
Freehold, New Jersey
Affordable Housing Rehabilitation
CPS managed the bid package, preconstruction, contract, and interior renovation under a county housing program.
Required paperwork was maintained at each step alongside the renovation, supporting the client through the program’s process.
New Jersey
Collision Center Project
We coordinated the trades and construction schedule, with supervision on site.
The final work and accounting were completed together, giving the client the final cost information when the work was finished.
Quakertown, Pennsylvania
Specialty Door Planning
CPS worked with the client’s team to confirm the type and size of a morgue door as part of planning the interior work.